Watercress Line

Coronavirus / Covid-19 Update

Our priority during the Coronavirus / Covid-19 outbreak, and the railway's closure, is on meeting our running costs. We need around £75,000 per month. Without this income, within a relatively short period we will exhaust our reserves which are so important us for our long term plans.

Although these are difficult times for all of us, we are asking you to consider providing financial support to the railway. With your support, ideally through a monthly standing order, the railway can be in a safe and good position to move forward rapidly when circumstances allow.

The amount is up to you as everyone’s circumstances are different, but please give as generously as you can. One-off donations would also be welcomed.

Thank you.

Visit our donation page to make a monthly gift or donate a single amount.

You can also text WATERCRESS to 70085 to donate £10. Texts cost £10 plus one standard rate message.

Miniature Railway Report 17 January

17th Jan 2015

Having regrouped following the Christmas festivities we have been back in harness at the Miniature Railway for the last two Saturdays. Good progress has been made in the following areas: &...

First Miniature Railway Train Back at Ropley

13th Dec 2014

Saturday 13th December 2014 marked the first arrival of a complete Miniature Railway train back at Ropley since the end of the 2012 operating season. All the track into Ropley has now ...

Miniature Railway Report 29 November

29th Nov 2014

I am pleased to announce that today we have laid the last track panels at the Ropley end of the Miniature Railway. There is still some ballasting required but I ...

Miniature Railway Report 12 October

12th Oct 2014

Apologies for the delay in producing this report which is due to my weekday work taking me to Scotland on numerous occasions. However, this has not interrupted our Saturday works ...

Loco Seen Running on Miniature Railway!

10th Aug 2014

Wednesday 6th August Thanks to David Ford who arranged this working day Wednesday saw Ben Spraggen with his digger, Brian Lawes with his dumper, Martin Pratt and myself hard at ...

Miniature Railway Report 4 August

4th Aug 2014

Following delivery of 20T of Ballast last week laying of the ballast along the route commenced Saturday 2nd of August. Just over 100m of the line has been covered plus ...

Moving the Miniature Railway

6th Jul 2014

Here is a brief overview of the weekend's activities to transfer the Miniature Railway's 40 foot Container:- Fri am Morley Slade disconnected the container supply power lead in ...