
Medstead - Here We Come!
14th May 2015
2014 was a hectic year for Signal Engineering with the Phase 2 commissioning of Ropley Signal Box in July, closely followed by the Network Rail “fringe” interface in November. In ...
14th May 2015
2014 was a hectic year for Signal Engineering with the Phase 2 commissioning of Ropley Signal Box in July, closely followed by the Network Rail “fringe” interface in November. In ...
18th Nov 2014
18 November 2014 Just two days after the final commissioning of the new "fringe” signalling at Alton, today saw the first train signalled across the boundary with Network Rail at 07.30 hrs ...
17th Nov 2014
17 November – Signal Engineering Report Yet another milestone in the history of the Mid Hants was achieved at 14.45 hrs on Sunday 16th November 2014 when the final stage of the "fringe&...
5th Sep 2014
At 17.30 on Thursday 4th September, a West Coast Rail Class 57 arrived in platform two at Alton with a convoy of three diesel’s for the MHR Gala the following ...
25th Jul 2014
Signal Engineering Report 25 July The Signal Engineering team that work on Mondays are affectionately known as the "Donut Gang". Why? Our little treat for the mid- morning cuppa is a ...
23rd Jul 2014
Signal Engineering Report 23 July We all know the old adage... you wait a long time for a bus, then two come along together. This has also happened to the MHR ...
5th Jul 2014
Signal Engineering Report - 5 July Further to my news item a couple of weeks ago, I can now confirm that Phase 2 of the Ropley signalling scheme was successfully commissioned on ...
14th Jun 2014
Signal Engineering Report - 14 June After several years of hard work at Ropley following the move into the old Netley signal box, commissioning of the final stage of the Ropley ...
13th Feb 2014
Wednesday 12 February – Signal Engineering Report When the Mid Hants Railway was born, there were only a couple of operational signals in use at Alresford. Over the years many more ...
7th Jan 2014
S & T Report - Monday 6 January 2014 A depleted S & T "Monday Gang" dragged themselves out of bed today on yet another wet and windy winters morning looking for ...
15th Oct 2013
Signal Engineering Report 14th October Last week, the Signal Engineering "Thursday Team" switched their working day to Friday to assist ‘the guvnor’ with the installation of the new ...
17th Sep 2013
17 September - Signal Engineering Report. Over the August Bank Holiday weekend and the week following, the Network Rail signal boxes at Farnham, Aldershot and Ash Vale were closed with control ...
1st Jul 2013
Monday 1 July 2013 – Signal Engineering Report Why is it that most outside jobs coincide with the coldest days of the year (see previous update entitled Extreme Signal Engineering) whilst those ...
20th May 2013
Monday 20 May - Signal Engineering Update Two weeks ago saw a major project underway in Ropley Box... the replacement of the Block Shelf with a new, deeper version to be ...
7th May 2013
Tuesday 7 May - Signal Engineering Department Report Following many months of installing, terminating and testing new wiring for the Phase 2 work at Ropley, last Thursday saw the installation of new ...
18th Apr 2013
Thursday 18 April - Signal Engineering Department Report Work still continues at Ropley as part of the phase 2 work and all new multicore cables that run between lineside location cases have ...